| Kollam Project HD |
| Date: 14/12/2021 |
Work has been completed | 100% Completed
Work completed
| Kollam Project HD |
| Date: 04/12/2021 |
Work has been completed | 100% Completed
Completed
| Kollam Project HD |
| Date: 24/03/2021 |
Work has been completed | 100% Completed
Completed
| Kollam Project HD |
| Date: 14/03/2021 |
Work has been completed | 100% Completed
Work Completed
| Kollam Project HD |
| Date: 09/03/2021 |
Work has been completed | 100% Completed
Work Completed
| Kollam Project HD |
| Date: 03/03/2021 |
Work has been completed | 100% Completed
Work Completed
| Kollam Project HD |
| Date: 02/03/2021 |
Work has been completed | 100% Completed
Work completed
| Kollam Project HD |
| Date: 28/02/2021 |
Work has been completed | 100% Completed
The work completed .
| Kollam Project HD |
| Date: 26/02/2021 |
Work has been completed | 100% Completed
The work completed .
| Kollam Project HD |
| Date: 25/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 24/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 23/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 22/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 20/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 19/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 18/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 17/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 16/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 15/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 14/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 13/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 12/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage
| Kollam Project HD |
| Date: 10/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 09/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 07/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 06/02/2021 |
Work has been completed | 100% Completed
The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 05/02/2021 |
| Kollam Project HD |
| Date: 04/02/2021 |
Work in progress | 97% Completed
The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 03/02/2021 |
Work in progress | 97% Completed
The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 02/02/2021 |
Work in progress | 97% Completed
The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 31/01/2021 |
Work in progress | 97% Completed
The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 26/01/2021 |
Work in progress | 97% Completed
The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.
| Kollam Project HD |
| Date: 11/01/2021 |
| Kollam Project HD |
| Date: 10/12/2020 |
| Kollam Project HD |
| Date: 27/11/2020 |
| Kollam Project HD |
| Date: 25/11/2020 |
| Kollam Project HD |
| Date: 27/10/2020 |
| Kollam Project HD |
| Date: 12/09/2020 |
Work in progress | 82% Completed
Agreement executed on 10/01/2019, Work in progress. Time of completion 12 months from the date of agreement ie., 9-01-2020. Total pipe laying length 3380m, laid 2770m .Time of extension up to 27-04-2020 under process.Testing of laid pipe line in progress 2760m tested.(82% progress)