Kollam Project HD
Date: 14/12/2021

Work has been completed | 100% Completed

Work completed

Kollam Project HD
Date: 04/12/2021

Work has been completed | 100% Completed

Completed

Kollam Project HD
Date: 24/03/2021

Work has been completed | 100% Completed

Completed

Kollam Project HD
Date: 14/03/2021

Work has been completed | 100% Completed

Work Completed

Kollam Project HD
Date: 09/03/2021

Work has been completed | 100% Completed

Work Completed

Kollam Project HD
Date: 03/03/2021

Work has been completed | 100% Completed

Work Completed

Kollam Project HD
Date: 02/03/2021

Work has been completed | 100% Completed

Work completed

Kollam Project HD
Date: 28/02/2021

Work has been completed | 100% Completed

The work completed .

Kollam Project HD
Date: 26/02/2021

Work has been completed | 100% Completed

The work completed .

Kollam Project HD
Date: 25/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 24/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 23/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 22/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 20/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 19/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 18/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 17/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 16/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 15/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 14/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 13/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 12/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage

Kollam Project HD
Date: 10/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 09/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 07/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 06/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 05/02/2021

Work has been completed | 100% Completed

The work completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Attached images

img img

Kollam Project HD
Date: 04/02/2021

Work in progress | 97% Completed

The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 03/02/2021

Work in progress | 97% Completed

The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 02/02/2021

Work in progress | 97% Completed

The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 31/01/2021

Work in progress | 97% Completed

The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 26/01/2021

Work in progress | 97% Completed

The work 97 % completed except 1000 m. road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Kollam Project HD
Date: 11/01/2021

Work in progress | 97% Completed

The work 97 % completed except road restoration work (Kollam corporation road). It was included in PWD Budget Work & now it is in Tendering Stage.

Attached images

img img img

Kollam Project HD
Date: 10/12/2020

Work in progress | 90% Completed

Out of 3120 m2 of road restoration work 1450 m2 has completed.

Attached images

img img img

Kollam Project HD
Date: 27/11/2020

Work in progress | 89% Completed

Laying of Clear water Pumping Main to Vadakkevila OHSR 89 % Completed. Gap closing work and Thrust block works are in progress.

Attached images

img img

Kollam Project HD
Date: 25/11/2020

Work in progress | 87% Completed

Gap Closing Work & Road restoration works are in progress. 87 % of work completed.

Attached images

img img

Kollam Project HD
Date: 27/10/2020

Work in progress | 85% Completed

Gap closing and Interconnection Work, Anchor block, Thrust block works are in progress.

Attached images

img img

Kollam Project HD
Date: 12/09/2020

Work in progress | 82% Completed

Agreement executed on 10/01/2019, Work in progress. Time of completion 12 months from the date of agreement ie., 9-01-2020. Total pipe laying length 3380m, laid 2770m .Time of extension up to 27-04-2020 under process.Testing of laid pipe line in progress 2760m tested.(82% progress)