Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme

Project Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme
Project Code CLTJJM022212477
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme
Status Completed
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 271800000
AS Number GO(Rt) No.134/2022/ WRD
TS Amount (Rs) 70200000
TS Number TS/2022-2023/2022/18793
Total Bill Submitted (Rs) 24206813
Total Bill Paid (Rs) 24206813
Population Benefitted 18031
Capacity in MLD 12.00
Actual Project Completion Date 30 Aug 2023
Coverage providing 460 nos FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Aug 2023 Work completed Kozhikode Project Dn AE5
26 Jul 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
11 Jul 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
27 Jun 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -21500m, 110mm - 2000m, 160mm - 3450m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
19 Jun 2023 90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m , 80mm GI - 2000m, 100mm GI - 500m Supplied. Laying work in progress, 90mm PE -20,880m, 110mm - 1650m, 160mm - 3300m, 75mm -1800m, 140mm PE -1100m, 80mm GI - 1000m, 100mm GI - 260m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/10/2022
Scheduled date of Completion of the Project 19 Mar 2023
Expected date of Completion 31/08/2023

Processing Dates

AS Date 23 Feb 2022
TS Date 24 Jun 2022