Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Aug 2023 |
Work completed |
Kozhikode Project Dn AE5 |
|
26 Jul 2023 |
90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
11 Jul 2023 |
90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
27 Jun 2023 |
90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -21500m, 110mm - 2000m, 160mm - 3450m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
19 Jun 2023 |
90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m , 80mm GI - 2000m, 100mm GI - 500m Supplied. Laying work in progress, 90mm PE -20,880m, 110mm - 1650m, 160mm - 3300m, 75mm -1800m, 140mm PE -1100m, 80mm GI - 1000m, 100mm GI - 260m laid, House connection work in progress - 580 HTCs provided.
|
Kozhikode Project Dn AE5 |
|