Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Aug 2023 Work completed Kozhikode Project Dn AE5
26 Jul 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
11 Jul 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
27 Jun 2023 90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -21500m, 110mm - 2000m, 160mm - 3450m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
19 Jun 2023 90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m , 80mm GI - 2000m, 100mm GI - 500m Supplied. Laying work in progress, 90mm PE -20,880m, 110mm - 1650m, 160mm - 3300m, 75mm -1800m, 140mm PE -1100m, 80mm GI - 1000m, 100mm GI - 260m laid, House connection work in progress - 580 HTCs provided. Kozhikode Project Dn AE5
09 Jun 2023 90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m Supplied. Laying work in progress, 90mm PE -20,880m, 110mm - 1650m, 160mm - 3300m, 75mm -1690m, 140mm PE -1100m laid, House connection work in progress - 574 HTCs provided. Kozhikode Project Dn AE5
03 Jun 2023 90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m Supplied. Laying work in progress, 90mm PE -20,800m, 110mm - 1650m, 160mm - 3300m, 75mm -1400m, 140mm PE -1100m laid, House connection work in progress - 540 HTCs provided. Kozhikode Project Dn AE5
27 May 2023 90mm PE - 23000m, 110mm PE - 2000, 160mm PE - 4000m, 75mm- 2000m Supplied. Laying work in progress, 90mm PE -20,500m, 110mm - 1174m, 160mm - 3300m, 75mm - 620m, 140mm PE -1100m laid, House connection work in progress - 450 HTCs provided. Kozhikode Project Dn AE5
16 May 2023 90mm PE - 20000m, 110mm PE - 900, 160mm PE - 2400m, 75mm- 2000m Supplied. Laying work in progress, 90mm PE -19,400m, 110mm - 1174m, 160mm - 1700m, 75mm - 620m laid, House connection work in progress - 390 HTCs provided. Kozhikode Project Dn AE5
10 May 2023 90mm PE - 18000m, 110mm PE - 900, 160mm PE - 2400m, 75mm- 2000m Supplied. Laying work in progress, 90mm PE -18,120m, 110mm - 1174m, 160mm - 1700m, 75mm - 620m laid, House connection work in progress - 378 HTCs provided. Kozhikode Project Dn AE5