Project | Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme |
---|---|
Project Code | CLTJJM022212477P1 |
Type | Package |
Main Project | Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 70200000 |
TS Number | TS/2022-2023/2022/18793 |
Technical specification | 1) 460 numbers of FHTCs 2)Designe,Testing and commissioning of 20 HP C/F pump set 3)Distribution 75mm PE - 2000m 90mm PE- 24000m 110mm PE -2000m 140mm PE - 1600m 160mm PE- 4500m Total =34100m |
Contractor | K RAMESHAN (Mob: 9447262192) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 19 Mar 2023 |
Expected date of Completion | 31/08/2023 |
TS Date | 24 Jun 2022 |
---|---|
Estimate Approval | 24 Jun 2022 |
Tender Closing | 20 Jul 2022 |
Technichal Pre-Qualification | 27 Aug 2022 |
Price bid opening | 06 Aug 2022 |
Workorder Date | 20 Sep 2022 |
---|---|
NA | 06 Oct 2022 |
Kozhikode Project Dn AE5 |
Date: 30/08/2023 |
Work has been completed | 100% Completed
Work completed, 580 HTCs provided. .
Kozhikode Project Dn AE5 |
Date: 29/08/2023 |
Work in progress | 98% Completed
90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. GI work in progress. .