Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme

Project Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme
Project Code CLTJJM022212477P1
Type Package
Main Project Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Phase III - Providing FHTC in Chakkittapara Panchayath -Package I- Providing FHTC by Augmentation of existing water supply scheme
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 70200000
TS Number TS/2022-2023/2022/18793
Technical specification 1) 460 numbers of FHTCs 2)Designe,Testing and commissioning of 20 HP C/F pump set 3)Distribution 75mm PE - 2000m 90mm PE- 24000m 110mm PE -2000m 140mm PE - 1600m 160mm PE- 4500m Total =34100m
Contractor K RAMESHAN (Mob: 9447262192)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/10/2022
Scheduled date of Completion as per agreement 19 Mar 2023
Expected date of Completion 31/08/2023

Processing Dates

TS Date 24 Jun 2022
Estimate Approval 24 Jun 2022
Tender Closing 20 Jul 2022
Technichal Pre-Qualification 27 Aug 2022
Price bid opening 06 Aug 2022

Approval Dates

Workorder Date 20 Sep 2022
NA 06 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE5
Date: 30/08/2023

Work has been completed | 100% Completed

Work completed, 580 HTCs provided. .

Kozhikode Project Dn AE5
Date: 29/08/2023

Work in progress | 98% Completed

90mm PE - 24000m, 110mm PE - 2000, 160mm PE - 4508m, 75mm- 2000m , 80mm GI - 2022m, 100mm GI - 534m, 125mm GI - 200m, 150mm GI- 1500m Supplied. Laying work in progress, 90mm PE -23750m, 110mm - 2000m, 160mm - 3550m, 75mm -2000m, 140mm PE -1500m, 65mm GI - 150m, 80mm GI - 1600m, 100mm GI - 260m, 125mm GI - 200m, 150mm GI - 124m laid, House connection work in progress - 580 HTCs provided. GI work in progress. .