Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m.

Project Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m.
Project Code KLMDC-LAC/ADS/SDF/KSCADC09205385
Type Main project
Funding Agency DC-LAC/ADS/SDF/KSCADC
Category Deposit Work
Type of scheme Water Supply
Scheme DC-LAC/ADS/SDF/KSCADC
Description Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m.
Status Completed
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 5000000
AS Number a4-5849/20 dated 3.9.20
TS Amount (Rs) 5000000
TS Number 09.09.2020
Total Bill Submitted (Rs) 3795426
Total Bill Paid (Rs) 3548965
Population Benefitted 100000
Capacity in MLD 1.00
Actual Project Completion Date Date is not specified
Coverage 100% completed
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath-Interconnection work with 200mm DI K9 Pumping main from Sasthamcotta WTP to 5LL OHSR Mukalumpuram in Mynagapally. Kollam Project Dn
2 Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m. Kollam Project Dn
3 Deposit work: Water supply improvements to mynagappally grama panchayath - Restoration of PWD road from WTP Sasthamcotta to mynagappally - KIIFB 2016-17- ANJILIMOOD - MYNAGAPPALLY SASTHAMCOTTA ROAD IN KOLLAM DISTRICT Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Apr 2021 Completed Kollam Project HD
20 Feb 2021 about to complete. finishing work going on Kollam Project HD
12 Feb 2021 Chamber works going on Kollam Project HD
11 Feb 2021 testing of pipes and completion works in progress Kollam Project HD
09 Feb 2021 836m pipe laid Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/11/2020
Scheduled date of Completion of the Project 08 Oct 2021
Expected date of Completion 19/01/2023

Processing Dates

AS Date 03 Sep 2020
TS Date 09 Sep 2020

Other details

Project Officers View