| Project | Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m. |
|---|---|
| Project Code | KLMDC-LAC/ADS/SDF/KSCADC09205385P1 |
| Type | Package |
| Main Project | Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m. |
| Funding Agency | DC-LAC/ADS/SDF/KSCADC |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DC-LAC/ADS/SDF/KSCADC |
| Description | Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m. |
| Status | Completed |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 5000000 |
| TS Number | 09.09.2021 |
| Technical specification | 800m layingp-300mm DI |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/12/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 08 Oct 2021 |
| Expected date of Completion | 03/08/2021 |
| TS Date | 09 Sep 2020 |
|---|---|
| Estimate Approval | 09 Aug 2020 |
| NIT Approval | 09 Aug 2020 |
| Tender Closing | 03 Nov 2020 |
| Technichal Pre-Qualification | 03 Nov 2020 |
| Price bid opening | 03 Nov 2020 |
| Workorder Date | 13 Oct 2020 |
|---|---|
| NA | 04 Nov 2020 |
| Kollam Project HD |
| Date: 08/03/2021 |
Work has been completed | 100% Completed
Completed.
| Kollam Project HD |
| Date: 05/03/2021 |
Work in progress | 99% Completed