Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Apr 2021 Completed Kollam Project HD
20 Feb 2021 about to complete. finishing work going on Kollam Project HD
12 Feb 2021 Chamber works going on Kollam Project HD
11 Feb 2021 testing of pipes and completion works in progress Kollam Project HD
09 Feb 2021 836m pipe laid Kollam Project HD
09 Feb 2021 WORK COMPLETED Kollam Project HD
07 Feb 2021 828metre of pipe laid and hydraulis testing compelted Kollam Project HD
04 Feb 2021 825 meter of DI pipe laid Kollam Project HD
24 Jan 2021 825 meter of DI pipe laid Kollam Project HD
03 Jan 2021 594 metres of Pipe laid(72%) Kollam Project HD