KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1

Project KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1
Project Code PKDKIIFB1118631P4
Type Package
Main Project KIIFB -17-18 - Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-2017-2018-CWSS TO KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 194200000
TS Number ORDER No. TS/2020-2021/2019/20557 Dated: 28-01-2021
Technical specification KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1
Contractor E.M.Poulose (Mob: 9447778116)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/12/2021
Scheduled date of Completion as per agreement 30 Sep 2022
Expected date of Completion 31/12/2024

Processing Dates

TS Date 28 Jan 2021
Estimate Approval 28 Jan 2021
NIT Approval 30 Jan 2021
Tender Closing 10 May 2021
Technichal Pre-Qualification 30 Apr 2021
Price bid opening 12 May 2021

Approval Dates

Workorder Date 31 Dec 2021
NA 31 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 08/05/2026

Work in progress | 86% Completed

Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid.

Chittur Project Dn - AE 3
Date: 06/05/2026

Work in progress | 86% Completed

Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid.