KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1
| Project |
KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1 |
| Project Code |
PKDKIIFB1118631P4 |
| Type |
Package |
| Main Project |
KIIFB -17-18 - Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
|
| Funding Agency |
KIIFB |
| Category |
KIIFB |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
KIIFB-2017-2018-CWSS TO KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1 |
| Status |
On-going |
| District |
Palakkad |
| Executing Office |
Chittur Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
194200000 |
| TS Number |
ORDER No. TS/2020-2021/2019/20557 Dated: 28-01-2021 |
| Technical specification |
KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1 |
| Contractor |
E.M.Poulose (Mob: 9447778116) |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
31/12/2021 |
| Scheduled date of Completion as per agreement |
30 Sep 2022 |
| Expected date of Completion |
31/12/2024 |
Processing Dates
| TS Date |
28 Jan 2021 |
| Estimate Approval |
28 Jan 2021 |
| NIT Approval |
30 Jan 2021 |
| Tender Closing |
10 May 2021 |
| Technichal Pre-Qualification |
30 Apr 2021 |
| Price bid opening |
12 May 2021 |
Approval Dates
| Workorder Date |
31 Dec 2021 |
| NA |
31 Dec 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Chittur Project Dn - AE 3 |
| Date: 08/05/2026 |
Work in progress | 86% Completed
Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid.
| Chittur Project Dn - AE 3 |
| Date: 06/05/2026 |
Work in progress | 86% Completed
Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid.