Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.

Project Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.
Project Code KNRGOK032212581P1
Type Package
Main Project Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.
Funding Agency GOK
Category RKI
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.
Status Completed
District Kannur
Executing Office Chavasseryparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 200000
TS Number TS/2022-23/2022/17876
Technical specification Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/09/2022
Scheduled date of Completion as per agreement 20 Sep 2022
Expected date of Completion 30/11/2022

Processing Dates

TS Date 20 Jul 2022
Estimate Approval 20 Jul 2022
NIT Approval 22 Aug 2022
Tender Closing 20 Aug 2022
Technichal Pre-Qualification 20 Aug 2022
Price bid opening 20 Aug 2022

Approval Dates

Workorder Date 22 Aug 2022
NA 01 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavasseryparamba WS Sn AE
Date: 21/11/2022

Work has been completed | 100% Completed

Work Completed. Bill Submitted..

Chavasseryparamba WS Sn AE
Date: 16/11/2022

Work in progress | 92% Completed

Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it.