| Chavasseryparamba WS Sn AE |
| Date: 21/11/2022 |
Work has been completed | 100% Completed
Work Completed. Bill Submitted.
| Chavasseryparamba WS Sn AE |
| Date: 16/11/2022 |
Work in progress | 92% Completed
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it
| Chavasseryparamba WS Sn AE |
| Date: 09/11/2022 |
Work in progress | 92% Completed
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it
| Chavasseryparamba WS Sn AE |
| Date: 04/11/2022 |
Work in progress | 90% Completed
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it