- Home
- Automation of Submersible Pump set - Imp...
Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy.
| Project |
Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy. |
| Project Code |
KNRGOK032212581 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
RKI |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy. |
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Chavasseryparamba WS Sn |
| AS Amount (Rs) |
200000
|
| AS Number |
6296/AE1(Operations)/2022/KWA |
| TS Amount (Rs) |
200000 |
| TS Number |
TS/2022-23/2022/17876 |
| Total Bill Submitted (Rs) |
197579 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
400 |
| Capacity in MLD |
0.10 |
| Actual Project Completion Date |
18 Nov 2022 |
| Coverage |
Ayiramkalam ST colony,Vilamana ST Colony Payam Panchayath, Karikkottakary ST Colony Ayyankunnu Panchayath, Sankarankandy ST Colony Thillankery Panchayath |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Automation of Submersible Pump set - Implimentation of Phase 1 (Stage 1 and 2) under RKI - Rural Pump Houses - RWSS to Ayirakkalam- Vilamana- Karikkottakari & Sankankandy. |
Chavasseryparamba WS Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 21 Nov 2022 |
Work Completed. Bill Submitted. |
Chavasseryparamba WS Sn AE |
|
| 16 Nov 2022 |
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it |
Chavasseryparamba WS Sn AE |
|
| 09 Nov 2022 |
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it |
Chavasseryparamba WS Sn AE |
|
| 04 Nov 2022 |
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it |
Chavasseryparamba WS Sn AE |
|
| 30 Sep 2022 |
Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it |
Chavasseryparamba WS Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
05/09/2022 |
| Scheduled date of Completion of the Project |
20 Sep 2022 |
| Expected date of Completion |
30/11/2022 |
Processing Dates
| AS Date |
15 Mar 2022 |
| TS Date |
01 Sep 2022 |