JJM 2021 – 22 –Setting up/ Upgradation / Operation of laboratories –Shifting of Quality Control Sub district Lab, Muvattupuzha
Project |
JJM 2021 – 22 –Setting up/ Upgradation / Operation of laboratories –Shifting of Quality Control Sub district Lab, Muvattupuzha |
Project Code |
EKMJJM09218443 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Shifting of Quality Control Sub district Lab, Muvattupuzha |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Aluva QC Sn Lab |
AS Amount (Rs) |
838600000
|
AS Number |
489/2021/WRD |
TS Amount (Rs) |
2191146 |
TS Number |
TS/2021-2022/2021/21895 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
457886 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
16 Jun 2022 |
Coverage |
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM 2021 – 22 –Setting up/ Upgradation / Operation of laboratories –Shifting of Quality Control Sub district Lab, Muvattupuzha |
Aluva QC Sn Lab |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
11 May 2023 |
completed and bill paid |
Kochi QC Sub Division - AEE |
|
04 May 2023 |
Completed and bill paid |
Kochi QC Sub Division - AEE |
|
01 Sep 2022 |
completed |
Aluva QCDL Aluva - AE |
|
16 Jun 2022 |
Work completed |
Aluva QCDL Aluva - AE |
|
08 May 2022 |
95% work completed |
Aluva QCDL Aluva - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/11/2021 |
Scheduled date of Completion of the Project |
26 Dec 2021 |
Expected date of Completion |
25/07/2022 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
13 Oct 2021 |