Project | JJM 2021 – 22 –Setting up/ Upgradation / Operation of laboratories –Shifting of Quality Control Sub district Lab, Muvattupuzha |
---|---|
Project Code | EKMJJM09218443P1 |
Type | Package |
Main Project | JJM 2021 – 22 –Setting up/ Upgradation / Operation of laboratories –Shifting of Quality Control Sub district Lab, Muvattupuzha |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Shifting of Quality Control Sub district Lab, Muvattupuzha |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva QC Sn Lab |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 2191146 |
TS Number | TS/2021-2022/2021/21895 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/11/2021 |
---|---|
Scheduled date of Completion as per agreement | 26 Dec 2021 |
Expected date of Completion | 31/12/2021 |
TS Date | 13 Oct 2021 |
---|---|
Estimate Approval | 13 Oct 2021 |
NIT Approval | 16 Oct 2021 |
Tender Closing | 29 Oct 2021 |
Price bid opening | 02 Nov 2021 |
Workorder Date | 12 Nov 2021 |
---|---|
NA | 19 Nov 2021 |
Aluva QCDL Aluva - AE |
Date: 01/09/2022 |
Work has been completed | 100% Completed