- Home
- 1- Jal Jeevan Mission (JJM) phase II Imp...
1- Jal Jeevan Mission (JJM) phase II Improvement to Water Supplay at Alumkunnu area in Anakkayam Panchayath- pipe line work 2-Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work
Project |
1- Jal Jeevan Mission (JJM) phase II Improvement to Water Supplay at Alumkunnu area in Anakkayam Panchayath- pipe line work 2-Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work |
Project Code |
MLPJJM022214931 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
1-Laying PVC pipe 160 mm dia -3300.00 m[ based on Alumkunnu]
Based on [Anakkayam Phase II]
1-Laying distribution line-Labour charge
2-Coast of meterials
3- Road restoration-PWD BM&BC
4- Road restoration-LSGDBY&Concrete road
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
269700000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
84296793 |
TS Number |
WRD/KWA-CE(NR)/EST-TS/4479/2022-26-3-2 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
2000 |
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
Alumkunnu area, Anakkayam Panchayath and varous wards of Anakkayam Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM) phase II Improvement to Water Supplay at Alumkunnu area in Anakkayam Panchayath- pipe line work |
Manjeri PH Sn |
|
2 |
Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work |
Manjeri PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2023 |
pipe supplied |
Malappuram PH Dn EE |
|
16 Sep 2023 |
Agreement Executed on 16/09/2023 |
Malappuram PH Dn EE |
|
07 Sep 2023 |
Work order Issued on 07/09/2023 |
Malappuram PH Dn EE |
|
09 Aug 2023 |
TS Issued on 09/08/2023 |
Malappuram PH Dn EE |
|
23 Feb 2022 |
AS Issued on 23/02/2022 |
Malappuram PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/01/2023 |
Scheduled date of Completion of the Project |
30 Apr 2023 |
Expected date of Completion |
30/04/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
09 Aug 2023 |