1- Jal Jeevan Mission (JJM) phase II - Anakkayam Panchayath works
Project |
1- Jal Jeevan Mission (JJM) phase II - Anakkayam Panchayath works |
Project Code |
MLPJJM022214931 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
1-Laying PVC pipe 160 mm dia -3300.00 m[ based on Alumkunnu]
Based on [Anakkayam Phase II]
1-Laying distribution line-Labour charge
2-Coast of meterials
3- Road restoration-PWD BM&BC
4- Road restoration-LSGDBY&Concrete road
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
269700000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
84296793 |
TS Number |
WRD/KWA-CE(NR)/EST-TS/4479/2022-26-3-2 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
2000 |
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
Alumkunnu area, Anakkayam Panchayath and varous wards of Anakkayam Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)- phase 2 UWSS to Anakkayam-jjm- phaseII-Package 2a construction of 5 MLD WTP and allied works 7.2 LL OHSR in Anakkayam pipe line work |
Manjeri PH Sn |
|
2 |
Jal Jeevan Mission (JJM) phase II Improvement to Water Supplay at Alumkunnu area in Anakkayam Panchayath- pipe line work |
Manjeri PH Sn |
|
3 |
Jal Jeevan Mission (JJM) Phase II UWSS to Anakkayam-package C Laying of distribution system in Anakkayam Panchayath |
Manjeri PH Sn |
|
4 |
Jal Jeevan Mission phase II UWSS to Anakkayam -JJM Phase II -laying and commissioning of 300 mm DI pumping main,installing and commossioning of pumpsets,laying of CWPM ,road restoration in Anakkayam Gramapanchayath- pipe line work |
Manjeri PH Sn |
|
5 |
Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work |
Manjeri PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Jun 2025 |
NE SCHEME WORK YET TO START |
Manjeri AE |
|
26 Jun 2025 |
new scheme work yet to start |
Manjeri AE |
|
25 Jun 2025 |
NEW SCHEME WORK YET TO START |
Manjeri AE |
|
18 Jun 2025 |
new scheme work yet to start |
Manjeri AE |
|
13 Jun 2025 |
NEW SCHME WORK YET TO START |
Manjeri AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/01/2023 |
Scheduled date of Completion of the Project |
30 Apr 2023 |
Expected date of Completion |
30/04/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
09 Aug 2023 |