Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work

Project Jal Jeevan Mssion(JJM) - Phase II UWSS to Anakkayam -JJM Phase II-Improvements to UWSS to Anakkayam -Extension of distribution lines from existing Scheme to provide FHTCs of Phase Iin Various wards of Anakkayam Gramapanchayath- pipe line work
Project Code MLPJJM022214931P2
Type Package
Main Project 1- Jal Jeevan Mission (JJM) phase II - Anakkayam Panchayath works
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description 1-Laying distribution line-Labour charge 2-Coast of meterials 3- Road restoration-PWD BM&BC 4- Road restoration-LSGDBY&Concrete road
Status On-going
District Malappuram
Executing Office Manjeri PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 74500000
TS Number 14297/2023-24
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/01/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 30/04/2023

Processing Dates

TS Date 19 Sep 2023
Estimate Approval 19 Sep 2023
Tender Closing 11 Oct 2023
Price bid opening 12 Oct 2023

Approval Dates

Workorder Date 30 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Manjeri AE
Date: 04/07/2025

Work in progress | 99% Completed

work in progress.

Manjeri AE
Date: 28/06/2025

Work in progress | 99% Completed

WORK IN PROGRESS.