DEPOSIT- KIIFB - 2017 - 18 - IMPROVEMENTS TO ETC POOMANGALAM - MAZHOOR - PADEPPANGADU - MADAKKADU ROAD KM 0/000 TO 13/551 - SHIFTING OF KWA UTILITIES - PHASE I - FROM ETC JUNCTION TO PADAPPENGAD (CH 0.000 TO CH:11.850.)-Pipeline Work

Project DEPOSIT- KIIFB - 2017 - 18 - IMPROVEMENTS TO ETC POOMANGALAM - MAZHOOR - PADEPPANGADU - MADAKKADU ROAD KM 0/000 TO 13/551 - SHIFTING OF KWA UTILITIES - PHASE I - FROM ETC JUNCTION TO PADAPPENGAD (CH 0.000 TO CH:11.850.)-Pipeline Work
Project Code KNRKIIFB082418005
Type Main project
Funding Agency KIIFB
Category Deposit Work
Type of scheme Water Supply
Scheme KIIFB
Description DEPOSIT- KIIFB - 2017 - 18 - IMPROVEMENTS TO ETC POOMANGALAM - MAZHOOR - PADEPPANGADU - MADAKKADU ROAD KM 0/000 TO 13/551 - SHIFTING OF KWA UTILITIES - PHASE I - FROM ETC JUNCTION TO PADAPPENGAD (CH 0.000 TO CH:11.850.)-Pipeline Work
Status On-going
District Kannur
Executing Office Thaliparamba WS Sub Dn
AS Amount (Rs) 27786000
AS Number EE/KRFB/KNR/AEE-II/J11/2021
TS Amount (Rs) 24900000
TS Number 27642/2024-2025
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSIT- KIIFB - 2017 - 18 - IMPROVEMENTS TO ETC POOMANGALAM - MAZHOOR - PADEPPANGADU - MADAKKADU ROAD KM 0/000 TO 13/551 - SHIFTING OF KWA UTILITIES - PHASE I - FROM ETC JUNCTION TO PADAPPENGAD (CH 0.000 TO CH:11.850.)-Pipeline Work Thaliparamba WS Sub Dn
2 DEPOSIT-KIIFB- 2017-18- IMPROVEMENTS TO ETC POOMANGALAM - MAZHOOR - PADEPPANGADU - MADAKKADU ROAD KM 0/000 TO 13/551-SHIFTING OF KWA UTILITIES - PHASE II - FROM PADAPPENGAD TO MADAKKAD JUNCTION (CH: 11/850 to CH: 13/551) AND BALANCE PORTION OF PHASE.I.-Pipeline Work Thaliparamba WS Sub Dn

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/06/2025
Scheduled date of Completion of the Project 19 Dec 2025
Expected date of Completion Date is not specified

Processing Dates

AS Date 14 Aug 2024
TS Date 21 Feb 2025

Other details

Project Officers View