DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work

Project DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Project Code KLMDEPO052314323P1
Type Package
Main Project DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Status Completed
District Kollam
Executing Office Kollam WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 227000
TS Number WRD/KWA-CE(SR)/EST_TS/9112/2023_26_1_1
Technical specification DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/05/2023
Scheduled date of Completion as per agreement 19 Jul 2023
Expected date of Completion 15/03/2024

Processing Dates

TS Date 12 May 2023
Estimate Approval 08 May 2023
NIT Approval 12 May 2023
Tender Closing 01 Jun 2023
Technichal Pre-Qualification 01 Jun 2023
Price bid opening 02 Jun 2023

Approval Dates

Workorder Date 06 Jun 2023
NA 20 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam WS Sn 2 - AE
Date: 11/01/2024

Work has been completed | 100% Completed

Work completed on 11/1/24. . Time of extension up to 15/1/2024 already got . .

Kollam WS Sn 2 - AE
Date: 09/01/2024

Work in progress | 99% Completed

Road crossing permission got and interconnection done. Replacing chocked connection are progressing. .