- Home
- Deposit work -Coast Guard -Improving wat...
Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house
Project |
Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house |
Project Code |
EKMDEPO09218563 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Karuvelippady WW Sub Dn |
AS Amount (Rs) |
95000000
|
AS Number |
E/II/HR/CG/kochi/HR |
TS Amount (Rs) |
2600000 |
TS Number |
18012/2021-22 |
Total Bill Submitted (Rs) |
14113925 |
Total Bill Paid (Rs) |
14113925 |
Population Benefitted |
500 |
Capacity in MLD |
0.20 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Coast Guard -Improving water supply to Coast Guard |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house |
Karuvelippady WW Sn 1 |
|
2 |
Deposit work - Coast Guard - Improving water supply to Coast Guard - supplying and erecting transformer 11KV and main HT panel, 630KVA Dry type transformer, HT metering cubical pannel with CT, PT, HT TOD meter, SSB 2 pannel incomer -800A TPN isolator, out going-250A TPN MCCB , 125 A TPN MCCB at Karuvelippady pump house - Part 1C |
Karuvelippady WW Sn 1 |
|
3 |
Deposit work – Coast Guard – Improving water supply to Coast Guard – Supplying and fixing flow meter including construction of chambers at Karuvelippady pump house – Part 1B |
Karuvelippady WW Sn 1 |
|
4 |
Deposit work - Improving water supply to Coast Guard by laying 150mm DI pipe from Karuvelipady pump house to Coast Guard ship support complex at Kalvathy - Part 2 |
Karuvelippady WW Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Apr 2024 |
One package completed, other packages in progress |
Karuvelippady AEE |
|
16 Apr 2024 |
One package completed, other packages in progress |
Karuvelippady AEE |
|
24 Feb 2024 |
One package completed, other packages in progress |
Karuvelippady AEE |
|
21 Feb 2024 |
One package completed, other packages in progress |
Karuvelippady AEE |
|
16 Feb 2024 |
One package completed, other packages in progress |
Karuvelippady AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/01/2022 |
Scheduled date of Completion of the Project |
30 Apr 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Sep 2021 |
TS Date |
14 Jan 2022 |