- Home
- Deposit work - Coast Guard - Improving w...
Deposit work - Coast Guard - Improving water supply to Coast Guard - supplying and erecting transformer 11KV and main HT panel, 630KVA Dry type transformer, HT metering cubical pannel with CT, PT, HT TOD meter, SSB 2 pannel incomer -800A TPN isolator, out going-250A TPN MCCB , 125 A TPN MCCB at Karuvelippady pump house - Part 1C
Project |
Deposit work - Coast Guard - Improving water supply to Coast Guard - supplying and erecting transformer 11KV and main HT panel, 630KVA Dry type transformer, HT metering cubical pannel with CT, PT, HT TOD meter, SSB 2 pannel incomer -800A TPN isolator, out going-250A TPN MCCB , 125 A TPN MCCB at Karuvelippady pump house - Part 1C |
Project Code |
EKMDEPO09218563P4 |
Type |
Package |
Main Project |
Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house
|
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work - Coast Guard - Improving water supply to Coast Guard - supplying and erecting transformer 11KV and main HT panel, 630KVA Dry type transformer, HT metering cubical pannel with CT, PT, HT TOD meter, SSB 2 pannel incomer -800A TPN isolator, out going-250A TPN MCCB , 125 A TPN MCCB at Karuvelippady pump house - Part 1C
|
Status |
On-going |
District |
Ernakulam |
Executing Office |
Karuvelippady WW Sn 1 |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
14700000 |
TS Number |
TS/2021-22/2021/39686 |
Technical specification |
Deposit work - Coast Guard - Improving water supply to Coast Guard - supplying and erecting transformer 11KV and main HT panel, 630KVA Dry type transformer, HT metering cubical pannel with CT, PT, HT TOD meter, SSB 2 pannel incomer -800A TPN isolator, out going-250A TPN MCCB , 125 A TPN MCCB at Karuvelippady pump house - Part 1C
|
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
10/05/2022 |
Scheduled date of Completion as per agreement |
25 Jul 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
TS Date |
21 Feb 2022 |
Estimate Approval |
01 Mar 2022 |
NIT Approval |
01 Mar 2022 |
Tender Closing |
07 Mar 2022 |
Technichal Pre-Qualification |
08 Mar 2022 |
Price bid opening |
09 Mar 2022 |
Approval Dates
Workorder Date |
26 Apr 2022 |
NA |
07 May 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Karuvelippady AEE |
Date: 30/04/2024 |
Work in progress | 28% Completed
Pre-delivery inspection conducted
.
Karuvelippady AEE |
Date: 17/04/2024 |
Work in progress | 28% Completed
Pre-delivery inspection conducted
.