Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work – Coast Guard – Improving water supply to Coast Guard – Supplying and fixing flow meter including construction of chambers at Karuvelippady pump house – Part 1B

Project Deposit work – Coast Guard – Improving water supply to Coast Guard – Supplying and fixing flow meter including construction of chambers at Karuvelippady pump house – Part 1B
Project Code EKMDEPO09218563P3
Type Package
Main Project Deposit work -Coast Guard -Improving water supply to Coast Guard - Supplying and erecting centrifugal pump set having discharge of 60lps against head of 60m ,replacing valves at Karuvelipady pump house
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work – Coast Guard – Improving water supply to Coast Guard – Supplying and fixing flow meter including construction of chambers at Karuvelippady pump house – Part 1B
Status On-going
District Ernakulam
Executing Office Karuvelippady WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 3000000
TS Number TS/2021-22/2021/39685
Technical specification Deposit work – Coast Guard – Improving water supply to Coast Guard – Supplying and fixing flow meter including construction of chambers at Karuvelippady pump house – Part 1B

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/11/2022
Scheduled date of Completion as per agreement 23 Mar 2023
Expected date of Completion 31/07/2023

Processing Dates

TS Date 25 Feb 2022
Estimate Approval 01 Mar 2022
NIT Approval 03 Mar 2022
Tender Closing 08 Mar 2022
Technichal Pre-Qualification 14 Jun 2022
Price bid opening 21 Jun 2022

Approval Dates

Workorder Date 04 Nov 2022
NA 23 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi PH Dn EE
Date: 14/02/2024

Work has been completed | 100% Completed

Work has been completed .

Karuvelippady AEE
Date: 31/01/2024

Work has been completed | 100% Completed

work completed .