AMRUT-2015-16 Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road
Project |
AMRUT-2015-16 Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road |
Project Code |
EKMAMRUT0217739 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-2015-16- Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road - AS received for an amount of Rs.3.65Crore vide Order No. G.O Rt. No. 534/2017/LSGD Dt. 23.02.2017.
Beneficiary - 58630 Nos |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi WW Sn 1 |
AS Amount (Rs) |
36500000
|
AS Number |
GO (Rt)No.534/2017/LSGD |
TS Amount (Rs) |
36500000 |
TS Number |
TS/TEWS(SR)/AMRUT/03/2017-18 |
Total Bill Submitted (Rs) |
26506716 |
Total Bill Paid (Rs) |
18096679 |
Population Benefitted |
58630 |
Capacity in MLD |
1.80 |
Actual Project Completion Date |
02 Jun 2021 |
Coverage |
Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. |
Karuvelippady WW Sn 1 |
|
2 |
Upgradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories |
Karuvelippady Sn 3 |
|
3 |
Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories |
Karuvelippady Sn 3 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Sep 2022 |
Package 1- AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. Work completed and final bill submitted. Revised estimate submitted to Circle office .Package - 2 Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories- Final Billsubmitted. Package- 3 Up-gradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories- Final Bill submited. |
karuvelippady AE |
|
12 Sep 2022 |
Package 1- AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. Work completed and final bill submitted. Revised estimate submitted to Circle office .Package - 2 Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories- Final Billsubmitted. Package- 3 Up-gradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories- Final Bill submited. |
Karuvelippady AEE |
|
07 Sep 2022 |
Package 1- AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. Work completed and final bill submitted. Revised estimate submitted to Circle office .Package - 2 Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories- Final Billsubmitted. Package- 3 Up-gradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories- Final Bill submited. |
karuvelippady AE |
|
06 Sep 2022 |
Package 1- AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. Work completed and final bill submitted. Revised estimate submitted to Circle office .Package - 2 Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories- Final Billsubmitted. Package- 3 Up-gradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories- Final Bill submited. |
Karuvelippady AEE |
|
03 Sep 2022 |
Package 1- AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation. Work completed and final bill submitted. Revised estimate submitted to Circle office .Package - 2 Upgradation of Electrical Installation inside pump house at Karuvelippady - Supply, erection, testing, commissioning and maintaining of 90 HP Centrifugal Pump set and accessories- Final Billsubmitted. Package- 3 Up-gradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories- Final Bill submited. |
Karuvelippady AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/11/2018 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
11 May 2017 |