AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation.

Project AMRUT 2015-16 Replacement of existing 525mm distribution cum pumping main with 600mm rider main from Karuvelippady to Koovappadam in Kochi Corporation.
Project Code EKMAMRUT0217739P1
Type Package
Main Project AMRUT-2015-16 Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2015-16- Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road - AS received for an amount of Rs.3.65Crore vide Order No. G.O Rt. No. 534/2017/LSGD Dt. 23.02.2017.
Status Completed
District Ernakulam
Executing Office Karuvelippady WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 36500000
TS Number TS/TEWS(SR)/AMRUT/03/2017-18
Technical specification Laying of 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road
Contractor NATHIPATHI ENGINEERS (Mob: 9629686068)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/11/2018
Scheduled date of Completion as per agreement 06 Aug 2018
Expected date of Completion 02/06/2021

Processing Dates

TS Date 11 May 2017
Estimate Approval 11 May 2017
NIT Approval 11 May 2017
Tender Closing 20 Dec 2017
Technichal Pre-Qualification 20 Dec 2017
Price bid opening 22 Dec 2017

Approval Dates

Workorder Date 07 Feb 2018
NA 19 Feb 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

karuvelippady AE
Date: 13/07/2023

Work has been completed | 100% Completed

Work completed and final bill submitted.

Karuvelippady AEE
Date: 16/09/2022

Work has been completed | 100% Completed

Work completed , extra items occurred so revised estimate submitted to circle office .