- Home
- Upgradation of Electrical Installation i...
Upgradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories
Project |
Upgradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories |
Project Code |
EKMAMRUT0217739P2 |
Type |
Package |
Main Project |
AMRUT-2015-16 Replacing the existing 525m distribution cum pumping main with 600mm DI K9 pipe rider pumping main from Karuvelippady pump house to Koovapadam OHSR along Santo Gopalan Road
|
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Upgradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Karuvelippady Sn 3 |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
36500000 |
TS Number |
TS/TECWS(SR)/AMRUT/03/2017-18 |
Technical specification |
Upgradation of Electrical Installation inside pump house at Karuvelippady -Supply, erection, testing, commissioning and maintaining of 30 HP Centrifugal pump set and accessories |
Contractor |
NATHIPATHI ENGINEERS (Mob: 9629686068) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
29/03/2021 |
Scheduled date of Completion as per agreement |
13 May 2021 |
Expected date of Completion |
15/03/2022 |
Processing Dates
TS Date |
11 May 2017 |
Estimate Approval |
01 Nov 2017 |
NIT Approval |
01 Nov 2017 |
Tender Closing |
18 Mar 2021 |
Technichal Pre-Qualification |
23 Mar 2021 |
Price bid opening |
23 Mar 2021 |
Approval Dates
Workorder Date |
29 Mar 2021 |
NA |
31 Mar 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Karuvelippady AEE |
Date: 13/07/2023 |
Work has been completed | 100% Completed
Work completed and final bill submitted.
Karuvelippady AEE |
Date: 16/09/2022 |
Work has been completed | 100% Completed
Work completed, Bill submitted to division office
.