JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.

Project JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.
Project Code CLTJJM09218391
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.
Status Completed
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 35000000
AS Number G.O.(Rt) No. 489/2021/WRD
TS Amount (Rs) 33400000
TS Number TS/2021-2022/2021/15666
Total Bill Submitted (Rs) 23029616
Total Bill Paid (Rs) 23029616
Population Benefitted 22788
Capacity in MLD 1.11
Actual Project Completion Date 30 Sep 2022
Coverage Kakkur panchayath

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath. Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Oct 2022 Work completed.1000 Connections provided. Kozhikode Project Dn AE5
30 Sep 2022 Work completed.1000 Connections provided. Kozhikode Project Dn AE5
28 Sep 2022 Pipe fully supplied, Laying work completed. 995 Connections provided, House connection in progress. Kozhikode Project Dn AE5
30 Sep 2022 Work completed, 1595 FHTCs completed Kozhikode Project Dn AE5
27 Sep 2022 Pipe fully supplied, 75mm PE -9580m, 90mm- 200m, 160mm - 42m, GI-124m laid. Total laid = 9946m. 980 FHTCs and 150 HTCs provided, House connection in progress. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/12/2021
Scheduled date of Completion of the Project 08 Jun 2022
Expected date of Completion 30/09/2022

Processing Dates

AS Date 18 Sep 2021
TS Date 23 Nov 2021

Other details

Project Officers View