JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.

Project JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.
Project Code CLTJJM09218391P1
Type Package
Main Project JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath.
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 33400000
TS Number TS/2021-2022/2021/15666
Technical specification "Providing 995 FHTC's by extending distribution line. Details of pipes ( 1) 75mm HDPE -9000m , 2) 90 mm HDPE-200m , 3)160 mm HDPE -150m ). Total = 9350m.
Contractor P V KABEER (Mob: 7012385858)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/12/2021
Scheduled date of Completion as per agreement 08 Jun 2022
Expected date of Completion 30/09/2022

Processing Dates

TS Date 23 Nov 2021
Estimate Approval 23 Nov 2021
Tender Closing 06 Dec 2021
Price bid opening 09 Dec 2021

Approval Dates

Workorder Date 09 Dec 2021
NA 18 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE5
Date: 30/09/2022

Work has been completed | 100% Completed

Work completed.1000 Connections provided. .

Kozhikode Project Dn AE5
Date: 29/09/2022

Work in progress | 98% Completed

Pipe fully supplied, Laying work completed. 995 Connections provided, House connection in progress. .