Project | JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath. |
---|---|
Project Code | CLTJJM09218391P1 |
Type | Package |
Main Project | JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JAL JEEVAN MISSION -Phase III -Kakkur Grama Panchayath Providing Functional household tap connections by the extension of existing water supply scheme in kakkur Grama Panchayath. |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 33400000 |
TS Number | TS/2021-2022/2021/15666 |
Technical specification | "Providing 995 FHTC's by extending distribution line. Details of pipes ( 1) 75mm HDPE -9000m , 2) 90 mm HDPE-200m , 3)160 mm HDPE -150m ). Total = 9350m. |
Contractor | P V KABEER (Mob: 7012385858) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 09/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 08 Jun 2022 |
Expected date of Completion | 30/09/2022 |
TS Date | 23 Nov 2021 |
---|---|
Estimate Approval | 23 Nov 2021 |
Tender Closing | 06 Dec 2021 |
Price bid opening | 09 Dec 2021 |
Workorder Date | 09 Dec 2021 |
---|---|
NA | 18 Dec 2021 |
Kozhikode Project Dn AE5 |
Date: 30/09/2022 |
Work has been completed | 100% Completed
Work completed.1000 Connections provided. .
Kozhikode Project Dn AE5 |
Date: 29/09/2022 |
Work in progress | 98% Completed
Pipe fully supplied, Laying work completed. 995 Connections provided, House connection in progress. .