Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Oct 2022 Work completed.1000 Connections provided. Kozhikode Project Dn AE5
30 Sep 2022 Work completed.1000 Connections provided. Kozhikode Project Dn AE5
28 Sep 2022 Pipe fully supplied, Laying work completed. 995 Connections provided, House connection in progress. Kozhikode Project Dn AE5
30 Sep 2022 Work completed, 1595 FHTCs completed Kozhikode Project Dn AE5
27 Sep 2022 Pipe fully supplied, 75mm PE -9580m, 90mm- 200m, 160mm - 42m, GI-124m laid. Total laid = 9946m. 980 FHTCs and 150 HTCs provided, House connection in progress. Kozhikode Project Dn AE5
06 Sep 2022 Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. Kozhikode Project Dn AE5
30 Aug 2022 Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. Kozhikode Project Dn AE5
25 Aug 2022 Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. Kozhikode Project Dn AE5
11 Aug 2022 Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 Connections provided, House connection in progress. Kozhikode Project Dn AE5
04 Aug 2022 Pipe fully supplied, 75mm PE -9000m, 90mm- 180m, GI-118m laid. Total laid = 9298m. 980 Connections provided, House connection in progress. Kozhikode Project Dn AE5