04 Oct 2022 | Work completed.1000 Connections provided. | Kozhikode Project Dn AE5 | |
30 Sep 2022 | Work completed.1000 Connections provided. | Kozhikode Project Dn AE5 | |
28 Sep 2022 | Pipe fully supplied, Laying work completed. 995 Connections provided, House connection in progress. | Kozhikode Project Dn AE5 | |
30 Sep 2022 | Work completed, 1595 FHTCs completed | Kozhikode Project Dn AE5 | |
27 Sep 2022 | Pipe fully supplied, 75mm PE -9580m, 90mm- 200m, 160mm - 42m, GI-124m laid. Total laid = 9946m. 980 FHTCs and 150 HTCs provided, House connection in progress. | Kozhikode Project Dn AE5 | |
06 Sep 2022 | Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. | Kozhikode Project Dn AE5 | |
30 Aug 2022 | Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. | Kozhikode Project Dn AE5 | |
25 Aug 2022 | Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 FHTCs and 150 HTCs provided, House connection in progress. | Kozhikode Project Dn AE5 | |
11 Aug 2022 | Pipe fully supplied, 75mm PE -9187m, 90mm- 200m, 160mm - 31m, GI-124m laid. Total laid = 9516m. 980 Connections provided, House connection in progress. | Kozhikode Project Dn AE5 | |
04 Aug 2022 | Pipe fully supplied, 75mm PE -9000m, 90mm- 180m, GI-118m laid. Total laid = 9298m. 980 Connections provided, House connection in progress. | Kozhikode Project Dn AE5 |