Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work
Project Code KNRJJM102315794
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work
Status On-going
District Kannur
Executing Office Mattannur PH Sn
AS Amount (Rs) 151700000
AS Number G.O.(Rt)No.897/2023/WRD
TS Amount (Rs) 4760000
TS Number 22168/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 15 Jun 2024
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work Mattannur PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jun 2026 work completed and final bill submitted Mattannur WS Sn
21 Apr 2026 road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) Mattannur WS Sn
13 Apr 2026 road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) Mattannur WS Sn
04 Apr 2026 road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) Mattannur WS Sn
26 Mar 2026 road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) Mattannur WS Sn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 22 Aug 2024
Expected date of Completion 30/11/2024

Processing Dates

AS Date 26 Oct 2023
TS Date 16 Dec 2023

Other details

Project Officers View