| Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work |
|---|---|
| Project Code | KNRJJM102315794P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission (JJM)-Jal Jeevan Mission -Kannur district -Koodali Panchayath - Reappropriation - Road reformation work - Karadi- Kodolipram- Pulpukkari Pipeline road (Common gravity main).-Pipeline Work |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 4760000 |
| TS Number | 22168/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 14 Jun 2024 |
| Expected date of Completion | 30/11/2024 |
| TS Date | 16 Dec 2023 |
|---|---|
| Estimate Approval | 16 Dec 2023 |
| NIT Approval | 18 Dec 2023 |
| Tender Closing | 28 Dec 2023 |
| Price bid opening | 29 Dec 2023 |
| Workorder Date | 01 Mar 2024 |
|---|---|
| NA | 16 Mar 2024 |
| Mattannur WS Sn |
| Date: 29/12/2025 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ).
| Mattannur WS Sn |
| Date: 20/12/2025 |
Work in progress | 25% Completed
road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ).