| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jun 2026 | work completed and final bill submitted | Mattannur WS Sn | |
| 21 Apr 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 13 Apr 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 04 Apr 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 26 Mar 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 18 Mar 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 09 Mar 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) 25 | Mattannur WS Sn | |
| 27 Feb 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 17 Feb 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn | |
| 04 Feb 2026 | road restoration work towards karadi from kodolipram started ( GSB & WMM work is going on ) | Mattannur WS Sn |