Project |
JJM- CWSS to Nellikuzhy Panchayath and Kothamangalam Municipality |
Project Code |
EKMJJM092111043 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM- CWSS to Nellikuzhy Panchayath and Kothamangalam Municipality |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
893300000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
466317000 |
TS Number |
TS/14807/2022-5-1-1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
33292 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Nellikuzhy panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-NELLIKUZHY PANCHAYATH -Package - I- Part - B - Production components - Well cum Pump house , Row water pumping main. |
Project Division Perumbavoor |
|
2 |
JJM-NELLIKUZHY PANCHAYATH-Package - I - Production components - Well cum Pump house , WTP & Row water pumping main |
Project Division Perumbavoor |
|
3 |
JJM-WSS to Nellikkuzhi Panchayath - package -II - Distribution components - laying distribution lines & Providing FHTC - General Civil work. |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
Notice issued to the contractor on 06-07-2023,10-07-2023,29-07-2023,16-08-2023 for urgently starting the work. Pipe supply order given. |
Piravam Project Sub Dn AE 2 |
|
07 Sep 2023 |
Pipe supplied not done-Notice issued to the contractor on 06-07-2023,10-07-2023,29-07-2023,16-08-2023 |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Pipe Supply not done ,Notice issued to the contractor on
06.07.2023,10.07.2023,29.07.2023,16.08.2023 |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Pipe Supply not done ,Notice issued to the contractor on
06.07.2023,10.07.2023,29.07.2023,16.08.2023 |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Site handed over to contractor . DI pipes will
be delivered in 30-45 days after receipt of the CIPET call letter. PVC Pipes order given. |
Piravam Project Sub Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/12/2022 |
Scheduled date of Completion of the Project |
28 May 2024 |
Expected date of Completion |
28/05/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
14 Dec 2022 |