Project | JJM-WSS to Nellikkuzhi Panchayath - package -II - Distribution components - laying distribution lines & Providing FHTC - General Civil work. |
---|---|
Project Code | EKMJJM092111043P1 |
Type | Package |
Main Project | JJM- CWSS to Nellikuzhy Panchayath and Kothamangalam Municipality |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-WSS to Nellikkuzhi Panchayath - package -II - Distribution components - laying distribution lines & Providing FHTC - General Civil work. |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 893300000 |
TS Number | WRD/KWA-CE(CR)/EST_ TS/14807/2022_5_1_1 |
Technical specification | JJM-WSS to Nellikuzhy Panchayath Package - II - Distribution components - Laying distribution lines & Providing FHTCs |
Contractor | Shaji K Mathew (Mob: 9447730150) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 14/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 17 Mar 2024 |
Expected date of Completion | 17/03/2024 |
TS Date | 12 Apr 2023 |
---|---|
Estimate Approval | 12 Apr 2023 |
NIT Approval | 12 Aug 2023 |
Tender Closing | 04 Feb 2023 |
Technichal Pre-Qualification | 04 Feb 2023 |
Price bid opening | 05 Jan 2023 |
Workorder Date | 18 Mar 2023 |
---|---|
NA | 12 Apr 2023 |
Piravam Project Sub Dn AE 2 |
Date: 15/04/2024 |
Work in progress | 10% Completed
90 mm &110 mm PVC 6 kg pipe laying in progress.Total pipe laid 90 MM PVC -4936 m, 110 mm PVC -270 m.
Piravam Project Sub Dn AE 2 |
Date: 27/03/2024 |
Work in progress | 10% Completed
90 mm &110 mm PVC 6 kg pipe laying in progress.Total pipe laid 90 MM PVC -4936 m, 110 mm PVC -270 m ..