Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 Notice issued to the contractor on 06-07-2023,10-07-2023,29-07-2023,16-08-2023 for urgently starting the work. Pipe supply order given. Piravam Project Sub Dn AE 2
07 Sep 2023 Pipe supplied not done-Notice issued to the contractor on 06-07-2023,10-07-2023,29-07-2023,16-08-2023 Piravam Project Sub Dn AE 2
24 Aug 2023 Pipe Supply not done ,Notice issued to the contractor on 06.07.2023,10.07.2023,29.07.2023,16.08.2023 Piravam Project Sub Dn AE 2
24 Aug 2023 Pipe Supply not done ,Notice issued to the contractor on 06.07.2023,10.07.2023,29.07.2023,16.08.2023 Piravam Project Sub Dn AE 2
24 Aug 2023 Site handed over to contractor . DI pipes will be delivered in 30-45 days after receipt of the CIPET call letter. PVC Pipes order given. Piravam Project Sub Dn AE 2
17 Aug 2023 Supply order for distribution lines placed by the contractor. Piravam Project Sub Dn AE 2
11 Aug 2023 Supply order for distribution lines placed by the contractor. Piravam Project Sub Dn AE 2
04 Aug 2023 Supply order for distribution lines placed by the contractor. Piravam Project Sub Dn AE 2
29 Jul 2023 Supply order for distribution lines placed by the contractor. Piravam Project Sub Dn AE 2
19 Jul 2023 Package I -Production components, TS issued Package 2-Agreement Executed Piravam Project Sub Dn AE 2