Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thaliparamba WS Sub Dn
Date: 27/06/2025

Work in progress | 90% Completed

Interconnection work with 900mm DI pipe pending. Finishing works pending

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 85% Completed

Road restoration work completed

Thaliparamba WS Section
Date: 30/04/2025

Work in progress | 65% Completed

DI completed. Road restoration work started.

Thaliparamba WS Section
Date: 01/02/2025

Work in progress | 46% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 27/11/2024

Work in progress | 45% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 11/11/2024

Work in progress | 45% Completed

OHSR's concrete work & plastering completed, DI Laying started

Thaliparamba WS Section
Date: 05/11/2024

Work in progress | 40% Completed

OHSR's concrete work & plastering completed

Thaliparamba WS Section
Date: 30/10/2024

Work in progress | 40% Completed

OHSR's concrete work & plastering completed

Thaliparamba WS Section
Date: 23/10/2024

Work in progress | 35% Completed

OHSR concrete work completed, plastering under progress

Thaliparamba WS Section
Date: 09/10/2024

Work in progress | 30% Completed

OHSR covering slab concrete completed

Thaliparamba WS Section
Date: 01/10/2024

Work in progress | 30% Completed

OHSR covering slab concrete completed

Thaliparamba WS Section
Date: 25/09/2024

Work in progress | 20% Completed

Tank work up to OHSR side wall concrete completed

Thaliparamba WS Section
Date: 18/09/2024

Work in progress | 10% Completed

Tank work up to deck slab completed

Thaliparamba WS Section
Date: 02/09/2024

Work in progress | 3% Completed

Tank work upto first bracing completed

Thaliparamba WS Section
Date: 26/06/2024

Work has started | 0% Completed

Work order issued on 16.03.2024

Thaliparamba WS Section
Date: 04/04/2024

Work has started | 0% Completed

Work order issued on 16.03.2024

Thaliparamba WS Dn EE
Date: 25/03/2024

Work has started | 0% Completed

Work Order issued on 16.03.2024.