Project | JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneIV &V |
---|---|
Project Code | KNRJJM092214220P1 |
Type | Package |
Main Project | JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneIV &V |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying Distribution line and providing 2899 FHTC .total distribution line proposed in this project is 105734m for main line and 12032m for laying rider line and parellel line for avoiding road crossing. |
Status | On-going |
District | Kannur |
Executing Office | Koothuparamba Project Sn No2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 289600000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/3689/2022_26_2_1 |
Technical specification | Laying Distribution line and providing 2899 FHTC .total distribution line proposed in this project is m for main line and m for laying rider line and parellel line for avoiding road crossing. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 16/02/2023 |
---|---|
Scheduled date of Completion as per agreement | 15 Feb 2024 |
Expected date of Completion | 15/02/2024 |
TS Date | 25 Nov 2022 |
---|---|
Estimate Approval | 25 Nov 2022 |
NIT Approval | 03 Dec 2022 |
Tender Closing | 21 Dec 2022 |
Technichal Pre-Qualification | 31 Dec 2022 |
Price bid opening | 05 Jan 2023 |
Workorder Date | 23 Jan 2023 |
---|---|
NA | 07 Feb 2023 |
Koothuparamba Proj AE 2 |
Date: 04/07/2025 |
Work in progress | 92% Completed
136354.13 m pipe laid 425 HTC and 1048 FHTC given..
Koothuparamba Proj AE 2 |
Date: 01/07/2025 |
Work in progress | 92% Completed