JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District
| Project |
JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District |
| Project Code |
KTMJJM08204290 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District |
| Status |
Completed |
| District |
Kottayam |
| Executing Office |
Kottayam PH Dn |
| AS Amount (Rs) |
61894000
|
| AS Number |
GO (Rt) No.541/2020/WRD |
| TS Amount (Rs) |
53300000 |
| TS Number |
TS/2020-2021/2020/13487 |
| Total Bill Submitted (Rs) |
27256987 |
| Total Bill Paid (Rs) |
27256987 |
| Population Benefitted |
100000 |
| Capacity in MLD |
18.50 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
100% |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
JJM - OHSR of 3LL Capacity |
Kottayam WW Sn 1 |
|
| 2 |
JJM - Pipeline Laying |
Kottayam WW Sn 1 |
|
| 3 |
JJM - Providing FHTC's |
Kottayam WW Sn 1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 16 Dec 2021 |
Total fhtcs given 3804 nos out of 4500 connections
Tank work cover slab completed,plastering work started
90mm pvc total 18000m laid
90mm HDPE pipe 3000m laid
|
Kottayam PH Dn EE |
|
| 18 Oct 2021 |
Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain |
Kottayam WW Sn 1 AE |
|
| 16 Oct 2021 |
Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain |
Kottayam WW Sn 1 AE |
|
| 13 Oct 2021 |
Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain |
Kottayam WW Sn 1 AE |
|
| 11 Oct 2021 |
Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain |
Kottayam WW Sn 1 AE |
|
| Review Date |
Review Message |
Review Attended By |
| 25 Jun 2021 |
Add dated photographs of work showing progress and response of consumers.
This work was actually arranged with single package.IF POSSIBLE CONVERT IT AS ONE INSTEAD OF THREE.
|
AEE |
Duration & Sanction dates
| Date of start of Project |
15/10/2020 |
| Scheduled date of Completion of the Project |
29 Mar 2021 |
| Expected date of Completion |
31/12/2021 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
29 Aug 2020 |