JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District

Project JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District
Project Code KTMJJM08204290
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District
Status Completed
District Kottayam
Executing Office Kottayam PH Dn
AS Amount (Rs) 61894000
AS Number GO (Rt) No.541/2020/WRD
TS Amount (Rs) 53300000
TS Number TS/2020-2021/2020/13487
Total Bill Submitted (Rs) 27256987
Total Bill Paid (Rs) 27256987
Population Benefitted 100000
Capacity in MLD 18.50
Actual Project Completion Date Date is not specified
Coverage 100%
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM - OHSR of 3LL Capacity Kottayam WW Sn 1
2 JJM - Pipeline Laying Kottayam WW Sn 1
3 JJM - Providing FHTC's Kottayam WW Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Dec 2021 Total fhtcs given 3804 nos out of 4500 connections Tank work cover slab completed,plastering work started 90mm pvc total 18000m laid 90mm HDPE pipe 3000m laid Kottayam PH Dn EE
18 Oct 2021 Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain Kottayam WW Sn 1 AE
16 Oct 2021 Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain Kottayam WW Sn 1 AE
13 Oct 2021 Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain Kottayam WW Sn 1 AE
11 Oct 2021 Total FHTC's provided so far is 3491(78%), 20800m (99%) pipeline laying work progressing and centering and shuttering for bottom of OHSR tank is completed. The delay in progress is due to LOCKDOWN, CONTAINMENT ZONES and heavy rain Kottayam WW Sn 1 AE

Project Review

See All Review messages
Review Date Review Message Review Attended By
25 Jun 2021 Add dated photographs of work showing progress and response of consumers. This work was actually arranged with single package.IF POSSIBLE CONVERT IT AS ONE INSTEAD OF THREE. AEE

Duration & Sanction dates

Date of start of Project 15/10/2020
Scheduled date of Completion of the Project 29 Mar 2021
Expected date of Completion 31/12/2021

Processing Dates

AS Date 21 Aug 2020
TS Date 29 Aug 2020

Other details

Project Officers View