| Project | JJM - Pipeline Laying |
|---|---|
| Project Code | KTMJJM08204290P3 |
| Type | Package |
| Main Project | JJM- 2020-2021- PHASE I- Laying Pipelines and Providing Functional household tap connections in Thiruvarpp Panchayath, Kottayam District |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | pipe line laying |
| Status | On-going |
| District | Kottayam |
| Executing Office | Kottayam WW Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 0 |
| TS Number | TS/2020-2021/2020/13487 |
| Technical specification | pipe line laying in thiruvarppu panchayath |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 02/11/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Mar 2021 |
| Expected date of Completion | 15/09/2021 |
| TS Date | 29 Aug 2020 |
|---|---|
| Estimate Approval | 29 Aug 2020 |
| NIT Approval | 30 Aug 2020 |
| Tender Closing | 10 Sep 2020 |
| Technichal Pre-Qualification | 29 Sep 2020 |
| Price bid opening | 14 Sep 2020 |
| Workorder Date | 30 Sep 2020 |
|---|---|
| NA | 14 Oct 2020 |
| Kottayam WW Sn 1 AE |
| Date: 18/10/2021 |
Work has been completed | 100% Completed
pipe laying work completed.
| Kottayam WW Sn 1 AE |
| Date: 16/10/2021 |
Work has been completed | 100% Completed
pipe laying work completed.