| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Nov 2022 | Work Completed. Bill Submitted. | Chavasseryparamba WS Sn AE | |
| 16 Nov 2022 | Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it | Chavasseryparamba WS Sn AE | |
| 09 Nov 2022 | Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it | Chavasseryparamba WS Sn AE | |
| 04 Nov 2022 | Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it | Chavasseryparamba WS Sn AE | |
| 30 Sep 2022 | Automation work completed except Vilamana Pumphouse. Starter installed at Vilamana Pumphouse was dameged due to thunder and lightning Directed the Contractor to replace it | Chavasseryparamba WS Sn AE |