Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 May 2022 | Clearing of site completed ,earth work excavation , protection work progressing, Pipe line works along PWD Road also in progress | Malappuram Project Dn | |
28 Apr 2022 | Clearing of site completed ,earth work excavation progressing, Pipe line works along PWD Road also in progress | Malappuram Project Dn | |
25 Apr 2022 | Site clearing completed, earth work progressing-Pipe line work along PWD road progressing | Malappuram Project Dn |