Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Nov 2022 |
Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY,Cherukara road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing along Panchayath roads |
Malappuram Project Dn |
|
26 Oct 2022 |
Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing. |
Malappuram Project Dn |
|
15 Oct 2022 |
Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing. |
Malappuram Project Dn |
|
13 Oct 2022 |
1. Package I - GLSR completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approved-Pipes supply started laying progressing. |
Malappuram Project Dn |
|
07 Oct 2022 |
1.package I - GLSR completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started |
Malappuram Project Dn |
|
30 Sep 2022 |
1.package I - GLSR roof salb completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started |
Malappuram Project Dn |
|
19 Sep 2022 |
1.package I - GLSR roof salb completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started |
Malappuram Project Dn |
|
14 Sep 2022 |
GLSR side wall work completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes |
Malappuram Project Dn |
|
09 Sep 2022 |
Package -I - GLSR side wall work completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes |
Malappuram Project Dn |
|
01 Sep 2022 |
Package -I - GLSR side wall III rd lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . |
Malappuram Project Dn |
|