Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Nov 2022 Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY,Cherukara road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing along Panchayath roads Malappuram Project Dn
26 Oct 2022 Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing. Malappuram Project Dn
15 Oct 2022 Package I - GLSR completed - Pipeline Along PWD road ( PMNA- CPLY road) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Design of net work approved-Pipes supply started laying progressing. Malappuram Project Dn
13 Oct 2022 1. Package I - GLSR completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design submitted for approval- Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approved-Pipes supply started laying progressing. Malappuram Project Dn
07 Oct 2022 1.package I - GLSR completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started Malappuram Project Dn
30 Sep 2022 1.package I - GLSR roof salb completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started Malappuram Project Dn
19 Sep 2022 1.package I - GLSR roof salb completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey , Design of net work submitted for approval -Pipes supply started Malappuram Project Dn
14 Sep 2022 GLSR side wall work completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes Malappuram Project Dn
09 Sep 2022 Package -I - GLSR side wall work completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes Malappuram Project Dn
01 Sep 2022 Package -I - GLSR side wall III rd lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed., Pipe line , FHTC work progressing 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . Malappuram Project Dn