| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Aug 2022 | Package -I - GLSR side wall I st lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . | Malappuram Project Dn | |
| 23 Aug 2022 | Package -I - GLSR side wall I st lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . | Malappuram Project Dn | |
| 15 Aug 2022 | Package -I - Haunch of concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work submitted for approval | Malappuram Project Dn | |
| 31 Jul 2022 | Package -I - Base slab concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work is in progress. | Malappuram Project Dn | |
| 11 Jul 2022 | Package -I - Base slab concrete delayed due to heavy rain - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work is in progress. | Malappuram Project Dn | |
| 01 Jul 2022 | steel work completed for floor slab Concrete delayed due to heavy rain. | Malappuram Project Dn | |
| 27 Jun 2022 | Package I -steel work for base slab progressing Pipe along PWD road completed | Malappuram Project Dn | |
| 22 Jun 2022 | Pcc completed,steel work of floor slab progressing | Malappuram Project Dn | |
| 11 Jun 2022 | Package I-Earth work completed,pcc for footing in progress,pipe line along PWD road completed (part ). package-II- Design of structure is in progress.Package III- Survey started | Malappuram Project Dn | |
| 02 Jun 2022 | Package I-Earth work completed,pcc for footing in progress,pipe line along PWD road completed (part ). package-II- Design of structure is in progress.Package III- Survey started | Malappuram Project Dn |