Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Aug 2022 Package -I - GLSR side wall I st lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . Malappuram Project Dn
23 Aug 2022 Package -I - GLSR side wall I st lift concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig - Supply order placed for pipes . 3.Package III - Survey completed, Design of net work submitted for approval -Supply order placed for pipes . Malappuram Project Dn
15 Aug 2022 Package -I - Haunch of concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work submitted for approval Malappuram Project Dn
31 Jul 2022 Package -I - Base slab concrete completed - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work is in progress. Malappuram Project Dn
11 Jul 2022 Package -I - Base slab concrete delayed due to heavy rain - Pipeline Along PWD road ( PMNA CPLY) completed. 2.Package II - Survey work completed , Design and preparation of structural drawing progressig . 3.Package III - Survey completed, Design of net work is in progress. Malappuram Project Dn
01 Jul 2022 steel work completed for floor slab Concrete delayed due to heavy rain. Malappuram Project Dn
27 Jun 2022 Package I -steel work for base slab progressing Pipe along PWD road completed Malappuram Project Dn
22 Jun 2022 Pcc completed,steel work of floor slab progressing Malappuram Project Dn
11 Jun 2022 Package I-Earth work completed,pcc for footing in progress,pipe line along PWD road completed (part ). package-II- Design of structure is in progress.Package III- Survey started Malappuram Project Dn
02 Jun 2022 Package I-Earth work completed,pcc for footing in progress,pipe line along PWD road completed (part ). package-II- Design of structure is in progress.Package III- Survey started Malappuram Project Dn