| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Jan 2025 | *Phase 1-Survey ,Design ,Supply,Laying &Commissioning Balance Distribution system with FHTC in Vazhayur Grama Panchayath of Malappuram District- Final biil Submitted Work closed. DLP upto 31/01/2025 * JJM Vazhayur-Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges -35% work completed.Road restoration work is not yet started | Malapuram Proj Dn AE 4 | |
| 07 Jan 2025 | *Phase 1-Survey ,Design ,Supply,Laying &Commissioning Balance Distribution system with FHTC in Vazhayur Grama Panchayath of Malappuram District- Final biil Submitted Work closed. DLP upto 31/01/2025 * JJM Vazhayur-Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges -35% work completed | Malapuram Proj Dn AE 4 | |
| 20 May 2024 | New work tender under process | Malapuram Proj Dn AE 4 | |
| 14 Feb 2024 | New work tender under process | Malapuram Proj Dn AE 4 | |
| 24 May 2023 | maintenance work is on going | Malapuram Proj Dn AE 4 | |
| 11 May 2023 | Interconnection work and road restoration work in progress at various wards | Malapuram Proj Dn AE 4 | |
| 05 May 2023 | Interconnection work and road restoration work in progress at various wards | Malapuram Proj Dn AE 4 | |
| 31 Jan 2023 | 4750 Nos of FHTCs has been provided and work has been due to shortage of GI pipe. There was a huge protest from public against trenching and demanded for GI pipe. Even after several meetings, it had been decided to short close the work and rearrange | Malapuram Proj Dn AE 4 | |
| 01 Aug 2022 | interconnection work and road restoration work in progress | Malapuram Proj Dn AE 4 | |
| 25 May 2022 | FHTC work in progress | Malapuram Proj Dn AE 4 |