Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Jan 2025 *Phase 1-Survey ,Design ,Supply,Laying &Commissioning Balance Distribution system with FHTC in Vazhayur Grama Panchayath of Malappuram District- Final biil Submitted Work closed. DLP upto 31/01/2025 * JJM Vazhayur-Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges -35% work completed.Road restoration work is not yet started Malapuram Proj Dn AE 4
07 Jan 2025 *Phase 1-Survey ,Design ,Supply,Laying &Commissioning Balance Distribution system with FHTC in Vazhayur Grama Panchayath of Malappuram District- Final biil Submitted Work closed. DLP upto 31/01/2025 * JJM Vazhayur-Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges -35% work completed Malapuram Proj Dn AE 4
20 May 2024 New work tender under process Malapuram Proj Dn AE 4
14 Feb 2024 New work tender under process Malapuram Proj Dn AE 4
24 May 2023 maintenance work is on going Malapuram Proj Dn AE 4
11 May 2023 Interconnection work and road restoration work in progress at various wards Malapuram Proj Dn AE 4
05 May 2023 Interconnection work and road restoration work in progress at various wards Malapuram Proj Dn AE 4
31 Jan 2023 4750 Nos of FHTCs has been provided and work has been due to shortage of GI pipe. There was a huge protest from public against trenching and demanded for GI pipe. Even after several meetings, it had been decided to short close the work and rearrange Malapuram Proj Dn AE 4
01 Aug 2022 interconnection work and road restoration work in progress Malapuram Proj Dn AE 4
25 May 2022 FHTC work in progress Malapuram Proj Dn AE 4