| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Feb 2021 | 165 Nos FHTC given ,pipe laying 90mm PVC 6.5 Km completed | Malapuram Proj Dn AE 4 | |
| 30 Jan 2021 | 91 FHTC given , Work started by transferring materials from another work to speedup FHTC | Malapuram Proj Dn AE 4 | |
| 26 Jan 2021 | 65 Nos FHTC given in State plan work .. Awaiting pipe materials of JJM work to speedup the work | Malapuram Proj Dn AE 4 | |
| 31 Dec 2020 | Delay in getting materials ,causes delay in providing FHTC | Malapuram Proj Dn AE 4 | |
| 24 Dec 2020 | supply order placed for pipes and spls | Malapuram Proj Dn AE 4 | |
| 24 Dec 2020 | waiting tender apvl | Malapuram Proj Dn AE 4 | |
| 20 Nov 2020 | Workoredr issued on 3/11/2020 | Malapuram Proj Dn AE 4 | |
| 17 Nov 2020 | agreement executed ,awaiting survey work arranged in state plan for finalizing the design and pipes requirement | Malapuram Proj Dn AE 4 | |
| 01 Nov 2020 | tender process | Malapuram Proj Dn AE 4 | |
| 11 Oct 2020 | tender proceess | Malapuram Proj Dn AE 4 |