| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Jul 2021 | 648 Fhtc and 38km pipe laying completed | Malapuram Proj Dn AE 4 | |
| 09 Jun 2021 | 581 FHTc and 24km pipe laying completed.. balance pipeline work progressing | Malapuram Proj Dn AE 4 | |
| 07 Jun 2021 | 22km pipe laying completed.. work now slowly progressing after lockdown | Malapuram Proj Dn AE 4 | |
| 01 Jun 2021 | Work held up due to lockdown | Malapuram Proj Dn AE 4 | |
| 18 May 2021 | Work heldup due to lock down | Malapuram Proj Dn AE 4 | |
| 22 Apr 2021 | 630 FHTC work progressing and 18Km pipe laying complted out of 90Km | Malapuram Proj Dn AE 4 | |
| 15 Apr 2021 | 600 FHTC work in progressing . 17km pipe laying complted | Malapuram Proj Dn AE 4 | |
| 24 Mar 2021 | About 16 km pipe laying and 450 FHTC works completed and other works in progress | Malapuram Proj Dn AE 4 | |
| 15 Mar 2021 | Pipe laying work & FHTC work ,now in good progress | Malapuram Proj Dn AE 4 | |
| 16 Feb 2021 | slowly progressing | Malapuram Proj Dn AE 4 |