Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Aug 2022 Final bill under scrutiny will be submitted to DN office within a couple of days Chalakudy AE 2
26 Aug 2022 Final bill under scrutiny will be submitted to DN office within a couple of days Chalakudy AE 2
25 Aug 2022 Final bill under scrutiny will be submitted to DN office within a couple of days Chalakudy AE 2
23 Aug 2022 Final bill under scrutiny will be submitted to DN office within a couple of days Chalakudy AEE
17 Aug 2022 cc 8 th and final bill submitted to sub division on 12-08-2022 Chalakudy AE 2
12 Aug 2022 cc 8 th and final bill submitted to sub division on 12-08-2022 Chalakudy AE 2
10 Aug 2022 Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. FIinal Bill under preparation. Chalakudy AE 2
09 Aug 2022 Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. FIinal Bill under preparation. Chalakudy AE 2
06 Aug 2022 Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. FIinal Bill under preparation. Chalakudy AE 2
05 Aug 2022 Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. FIinal Bill under preparation. Chalakudy AE 2