| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Aug 2022 | Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. Bill under preparation. | Chalakudy AE 2 | |
| 30 Jul 2022 | Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. Bill under preparation. | Chalakudy AE 2 | |
| 29 Jul 2022 | Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. Bill under preparation. | Chalakudy AE 2 | |
| 27 Jul 2022 | Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. | Chalakudy AE 2 | |
| 25 Jul 2022 | Work completed except bridge crossing at Kappathode .This pipe line crossing work will be arranged through JJM Phase II project after getting the sanction from firm KRFB. | Chalakudy AE 2 | |
| 22 Jul 2022 | 200 mm DI PIPE Laying 96%Work completed, 2108 Nos FHTCs provided. | Chalakudy AE 2 | |
| 21 Jul 2022 | 200 mm DI PIPE Laying 95%Work completed, 2108 Nos FHTCs provided. | Chalakudy AE 2 | |
| 20 Jul 2022 | 200 mm DI PIPE Laying 95%Work completed, 2108 Nos FHTCs provided. | Chalakudy AE 2 | |
| 19 Jul 2022 | 200 mm DI PIPE Laying 95%Work completed, 2108 Nos FHTCs provided. | Chalakudy AE 2 | |
| 16 Jul 2022 | 200 mm DI PIPE Laying 95%Work completed, 2108 Nos FHTCs provided. | Chalakudy AE 2 |