| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 21 Mar 2022 | cc 7 th and part bill submitted to sub division on 21-03-2022 | Chalakudy AE 2 | |
| 21 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 19 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 18 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 15 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 14 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1935Nos FHTCs provided. | Chalakudy AE 2 | |
| 10 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1894Nos FHTCs provided. | Chalakudy AE 2 | |
| 08 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1764Nos FHTCs provided. | Chalakudy AE 2 | |
| 07 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1764Nos FHTCs provided. | Chalakudy AE 2 |