| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Apr 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 31 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 30 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 29 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 28 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 27 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 25 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 24 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 23 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 | |
| 22 Mar 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment | Palakkad Proj AE 3 |