Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
16 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
15 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
12 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
11 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
10 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
09 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
08 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor supplied, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
06 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2850 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3
05 May 2023 Intake well - structural works completed,180HP VT pump sets 3 nos supplied,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed , scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -2780 /3080 completed balance pipes to be supplied by contractor ,road crossing sanction from KRFB waiting. WTP- structural & aluminium fabrication works completed ,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 1.41Cr+1.83 Cr pending for the payment Palakkad Proj AE 3