| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champers concrete completed, errection works on going ,additional retaining wall completed. RWPM -3525.85 m completed balance pipes to be supplied by the contractor, Panchayath road restoration work completed, WTP- structural & aluminum fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 04 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champers concrete completed, errection works on going ,additional retaining wall completed. RWPM -3525.85 m completed balance pipes to be supplied by the contractor, Panchayath road restoration work completed, WTP- structural & aluminum fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 03 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champers concrete completed, errection works on going ,additional retaining wall completed. RWPM -3525.85 m completed balance pipes to be supplied by the contractor, Panchayath road restoration work completed, WTP- structural & aluminum fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 01 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champers concrete completed, errection works on going ,additional retaining wall completed. RWPM -3525.85 m completed balance pipes to be supplied by the contractor, Panchayath road restoration work completed, WTP- structural & aluminum fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 30 Jun 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champers concrete completed, errection works on going ,additional retaining wall completed. RWPM -3525.85 m completed balance pipes to be supplied by the contractor, Panchayath road restoration work completed, WTP- structural & aluminum fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 10 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -3680 m completed balance pipes to be supplied by the contractor,Panchayath road restoration work completed, WTP- structural & aluminium fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work completed ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Project Dn AE | |
| 07 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -3680 m completed balance pipes to be supplied by the contractor,Panchayath road restoration work completed, WTP- structural & aluminium fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 06 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos erecting completed,415 KVA transformer supplied, erecting works on going ,aluminum fabrication works completed. Booster Pump house- structural & aluminum fabrication works completed,132 KV/215 HP motor ettection work completed, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -3680 m completed balance pipes to be supplied by the contractor,Panchayath road restoration work completed, WTP- structural & aluminium fabrication works completed ,CUG valve , electro mechanical works progress, clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 05 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor ettection work completed, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -3680 m completed balance pipes to be supplied by the contractor,Panchayath road restoration work completed, WTP- structural & aluminium fabrication works completed ,CUG valve , electro mechanical works progress,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 | |
| 04 Jul 2023 | Intake well - structural works completed,180HP VT pump sets 3 nos errection completed,415 KVA transformer supplied,errection works on going ,aluminium fabrication works completed. Booster Pump house- structural & aluminium fabrication works completed,132 KV/215 HP motor ettection work completed, scour champer concrete completed,errection works on going ,additional retaining wall completed. RWPM -3680 m completed balance pipes to be supplied by the contractor,Panchayath road restoration work completed, WTP- structural & aluminium fabrication works completed ,CUG valve , electro mechanical works progress,clariflocculatior bridge work on going ,filter bed works on going. CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid balance pipes to be supplied by contractor Part bills of amount 168.642 Cr pending for the payment. | Palakkad Proj AE 3 |