Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Mar 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
03 Mar 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
24 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
23 Feb 2022 Part bill for Rs 64.11 lakhs submitted to FM for package 3 Adoor Project Dn EE
23 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
20 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
17 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
16 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
15 Feb 2022 Pipe line work completed. House connection shifting in progress. Adoor Project Dn AE3
13 Feb 2022 Pipe laying completed. Line charging in progress. Altration of house connections in progress Adoor Project Dn AE3